Budget Exceed error is not prompting while releasing WBS in PS

$
0
0

Dear Concern,

 

I have created a project (CJ20N) and set planned amount 101 bdt. I have given budget (IM52) 1 bdt. while i tried to release WBS element, it allowed me to release without prompting any budget exceed error.

 

Please help me to find out the root cause of the above mentioned issue. I need to activate the budget checking so that it throws error if the project planned cost is higher than the budget value.

 

Regards,

Farzana