Manually Changing Planning Method In Planning Board

$
0
0

Hi Experts,

 

I have set a particular project profile planning method to open planning for both both basic and forecast. In addition, I have set scheduling scenario to free scheduling. Per other threads and available SAP guidance this can be changed at a project level from the project planning board by selecting options and scheduling tab. However, when I go to there, the fields are not available to do so. I am operating on ECC 6.0 / EHP 7. Can someone advise if this ability has been moved or taken away or if it's visibility is controlled by some additional configuration or through an OSS note?

 

Thank you,

Kevin